Lesson

💡

The grantee faced some challenges during project implementation in Iraq, but due to a well-developed risk mitigation plan, the grantee was able to manage. For instance, the grantee had anticipated the risk of the non-cooperation of some Governorate Councils, so when two of six identified Councils withdrew from the initiative, the grantee took rapid action to replace them. The Councils were absorbed into project activities without much loss of time, and the grantee and its partner organizations managed to build trust and understanding with the two added Councils rather quickly.