Lesson

💡

The project’s effectiveness was also undermined by the lack of an effective decision-making arrangement between the grantee’s executive bureau and the office for project implementation. Because decisions could not be made on time, there were delays and changes to activities, and most of them were not completed. Lack of monitoring prevented any adjustment of the activities to achieve the expected results.