Lesson Learned: Strengthening Governance and Democratization Processes in Kenya and the East and Central Africa Region

Although most of the project activities were directly relevant to the objective of strengthening the electoral process in Kenya, most of the activities were designed as a series of one-time efforts. This scattered nature lacked the programmatic links and followed-up needed to be effective beyond the activity level. Failure to collect outcome data made impact difficult to assess beyond the individual level. In order to achieve outcomes beyond outputs, follow-up efforts would have been needed in all four activity areas.
Project Partner
Institute For Education In Democracy
Project Description
The main objective of the project was to strengthen the capacity grassroots organizations, and enhance the participation of citizens in governance to promote a democratic culture in Kenya and in eastern and central Africa. While some project activities were highly relevant and empowering to individual beneficiaries, others lacked follow-up. Among the project’s successes were the election observation trainings which had a multiplier effect with grassroots organizations. Following the workshop trainings, 12 observation groups were established to monitor the Kenyan election of 2013, all of which later obtained a long-term accreditation status as election observers. In general, the project was activity-driven which made outcomes and institutional impact difficult to assess. Project design showed some weaknesses, as several challenges that appeared during implementation could have been anticipated by the grantee beforehand. For example, the shortage of staff and a better coordination with the electoral timeline in Kenya could have ensured a smoother implementation.
Evaluation Date
May 2013
Country
LESSON

Lesson Learned: Strengthening Governance and Democratization Processes in Kenya and the East and Central Africa Region

A part of the project entailed translating sections of the ACE Electoral Knowledge Network website into Swahili to increase access to voter education. However, the Swahili site ended up not generating much traffic. Part of the reason was the lack of publicity and outreach. Another was the lack of relevance for local CSO’s in Kenya. All of the Kenyans interviewed said they would rather access technical information in English because Swahili did not have the technical vocabulary needed.
Project Partner
Institute For Education In Democracy
Project Description
The main objective of the project was to strengthen the capacity grassroots organizations, and enhance the participation of citizens in governance to promote a democratic culture in Kenya and in eastern and central Africa. While some project activities were highly relevant and empowering to individual beneficiaries, others lacked follow-up. Among the project’s successes were the election observation trainings which had a multiplier effect with grassroots organizations. Following the workshop trainings, 12 observation groups were established to monitor the Kenyan election of 2013, all of which later obtained a long-term accreditation status as election observers. In general, the project was activity-driven which made outcomes and institutional impact difficult to assess. Project design showed some weaknesses, as several challenges that appeared during implementation could have been anticipated by the grantee beforehand. For example, the shortage of staff and a better coordination with the electoral timeline in Kenya could have ensured a smoother implementation.
Evaluation Date
May 2013
Country
LESSON

Lesson Learned: Strengthening Governance and Democratization Processes in Kenya and the East and Central Africa Region

There was a lack of adequate staffing for project activities as staff was also tasked with other work. This delayed some activities and a more coherent implementation of outputs following the Kenyan electoral cycle timeline. Lack of staff capacity could have been mitigated by the grantee at the design phase through increasing the number of project staff, adopting a cascade training approach, and/or providing small subgrants to partners in Kenya which could also help to strengthen organizations at the grassroots level.
Project Partner
Institute For Education In Democracy
Project Description
The main objective of the project was to strengthen the capacity grassroots organizations, and enhance the participation of citizens in governance to promote a democratic culture in Kenya and in eastern and central Africa. While some project activities were highly relevant and empowering to individual beneficiaries, others lacked follow-up. Among the project’s successes were the election observation trainings which had a multiplier effect with grassroots organizations. Following the workshop trainings, 12 observation groups were established to monitor the Kenyan election of 2013, all of which later obtained a long-term accreditation status as election observers. In general, the project was activity-driven which made outcomes and institutional impact difficult to assess. Project design showed some weaknesses, as several challenges that appeared during implementation could have been anticipated by the grantee beforehand. For example, the shortage of staff and a better coordination with the electoral timeline in Kenya could have ensured a smoother implementation.
Evaluation Date
May 2013
Country
LESSON

Lesson Learned: Strengthening Governance and Democratization Processes in Kenya and the East and Central Africa Region

To enhance the capacity of the newly established Office of the Registrar of Political Parties in Kenya, the grantee organized study tours to Canada, Mexico and Ghana. While the tours were useful in raising awareness of participants, there was no plan for how new knowledge and recommendations should be incorporated into the organization. Study tours should have been part of a broader institutional capacity building effort that also provided follow-up activities.
Project Partner
Institute For Education In Democracy
Project Description
The main objective of the project was to strengthen the capacity grassroots organizations, and enhance the participation of citizens in governance to promote a democratic culture in Kenya and in eastern and central Africa. While some project activities were highly relevant and empowering to individual beneficiaries, others lacked follow-up. Among the project’s successes were the election observation trainings which had a multiplier effect with grassroots organizations. Following the workshop trainings, 12 observation groups were established to monitor the Kenyan election of 2013, all of which later obtained a long-term accreditation status as election observers. In general, the project was activity-driven which made outcomes and institutional impact difficult to assess. Project design showed some weaknesses, as several challenges that appeared during implementation could have been anticipated by the grantee beforehand. For example, the shortage of staff and a better coordination with the electoral timeline in Kenya could have ensured a smoother implementation.
Evaluation Date
May 2013
Country
LESSON

Lesson Learned: Strengthening Governance and Democratization Processes in Kenya and the East and Central Africa Region

A part of the project entailed translating sections of the ACE Electoral Knowledge Network website into Swahili. But there was already more than a decade’s worth of good materials developed in the region in local languages that could have been uploaded to ACE. Before investing in this effort, a needs assessment should have been done to see if the lack of ACE-type material in Swahili was a major constraint to the achievement of the project’s intended outcomes and to determine which topics, if any, should be translated.
Project Partner
Institute For Education In Democracy
Project Description
The main objective of the project was to strengthen the capacity grassroots organizations, and enhance the participation of citizens in governance to promote a democratic culture in Kenya and in eastern and central Africa. While some project activities were highly relevant and empowering to individual beneficiaries, others lacked follow-up. Among the project’s successes were the election observation trainings which had a multiplier effect with grassroots organizations. Following the workshop trainings, 12 observation groups were established to monitor the Kenyan election of 2013, all of which later obtained a long-term accreditation status as election observers. In general, the project was activity-driven which made outcomes and institutional impact difficult to assess. Project design showed some weaknesses, as several challenges that appeared during implementation could have been anticipated by the grantee beforehand. For example, the shortage of staff and a better coordination with the electoral timeline in Kenya could have ensured a smoother implementation.
Evaluation Date
May 2013
Country
LESSON

Lesson Learned: Enhancing the Capacity for Inclusive Local Governance through Synergies and Sustainable Linkages between Communities and Government in North Afghanistan

A major deficiency in overall management rested with the centralization of decision-making by ACTED Kabul. The project design had a “generic” quality to it, and it is apparent that operations managers in the field had no input into decision-making, including work and expenditure planning. The weakness of two-way communications at this level reduced the opportunity for the project to learn from experience and adapt operational plans accordingly.
Project Partner
ACTED
Project Description
Enhancing the Capacity for Inclusive Local Governance in Northern Afghanistan was generally effective as a training project, but its overall design was not well-aligned with the overall objectives specified. The project made a difference for the trainees who benefited from the course provided, but did not contribute much to the institutional results linked to enhancing inclusive local governance. The grantee was a well-known international NGO. This was strength in some ways, but may have been a weakness in others. The project design had a “generic” quality to it, suggesting a lack of attention to the specific needs in the project sites that were addressed. Further, the lack of engagement with the project by ACTED Kabul at a management level, along with the absence of decentralization of decision-making to the local level, undermined project effectiveness.
Evaluation Date
April 2013
Country
LESSON

Lesson Learned: Enhancing the Capacity for Inclusive Local Governance through Synergies and Sustainable Linkages between Communities and Government in North Afghanistan

Project strategy for training was well-prepared, taking account of the needs and characteristics of potential trainees in the area. The training-of-trainers course, training curriculum and methodology, all designed by a contracted provider, appear to have been well-done, and matched appropriately to trainee learning needs and capabilities of the beneficiaries in Afghanistan.
Project Partner
ACTED
Project Description
Enhancing the Capacity for Inclusive Local Governance in Northern Afghanistan was generally effective as a training project, but its overall design was not well-aligned with the overall objectives specified. The project made a difference for the trainees who benefited from the course provided, but did not contribute much to the institutional results linked to enhancing inclusive local governance. The grantee was a well-known international NGO. This was strength in some ways, but may have been a weakness in others. The project design had a “generic” quality to it, suggesting a lack of attention to the specific needs in the project sites that were addressed. Further, the lack of engagement with the project by ACTED Kabul at a management level, along with the absence of decentralization of decision-making to the local level, undermined project effectiveness.
Evaluation Date
April 2013
Country
LESSON

Lesson Learned: Enhancing the Capacity for Inclusive Local Governance through Synergies and Sustainable Linkages between Communities and Government in North Afghanistan

What is required is a very long-term engagement to build the necessary capacities. For efforts to support democratic development and an active and dynamic civil society in Afghanistan, prospects of sustainability are yet more limited.
Project Partner
ACTED
Project Description
Enhancing the Capacity for Inclusive Local Governance in Northern Afghanistan was generally effective as a training project, but its overall design was not well-aligned with the overall objectives specified. The project made a difference for the trainees who benefited from the course provided, but did not contribute much to the institutional results linked to enhancing inclusive local governance. The grantee was a well-known international NGO. This was strength in some ways, but may have been a weakness in others. The project design had a “generic” quality to it, suggesting a lack of attention to the specific needs in the project sites that were addressed. Further, the lack of engagement with the project by ACTED Kabul at a management level, along with the absence of decentralization of decision-making to the local level, undermined project effectiveness.
Evaluation Date
April 2013
Country
LESSON

Lesson Learned: Coalition against Poverty: Oil Revenue under Public Oversight

Anecdotal evidence suggested that highlighting contradictions between constitutional or legal principles and the current operations of many local and regional institutions in Kazakhstan has raised civic awareness. While impact on corporate policy or behaviour was not measured it was widely believed that the challenging approach taken - if supported by bilateral donors - would not have been welcome in this isolated environment remote from Western influence.
Project Partner
Sange Research Center
Project Description
The project aimed to improve understanding of transparency and accountability in the governance of the extractive sector in Kazakhstan. The project emphasised understanding of the extractive sector’s impact on poverty, environmental vulnerability, labour conditions and rights, income and access to services. Activities focused on multiple stakeholders operating in five regions of Kazakhstan, with the goal of developing more transparent, accountable, and effective institutions that would expand citizen participation and promote more sustainable development. The project targeted areas where extractive industries are important economic actors and where civil society needs increased capacity or support to more effectively engage in governance. Project activities tackled the gap in access to usable outside information through research, analysis, and outreach. Collaborative learning tactics supported increased local engagement.
Evaluation Date
April 2013
Country
LESSON

Lesson Learned: Enlarging the Social Base for Democracy and the Rule of Law in Egypt

The project’s responses to unexpected problems in security were reasonable and effective, but were ad hoc in nature rather than based on any risk assessment and management strategy. Particularly since the project was designed with Egypt’s election schedule in mind, the risk of delays and disruptions might have been foreseeable.
Project Partner
Cairo Institute for Human Rights Studies
Project Description
The context of the project was the period of intense political activity and instability in Egypt following the 2011 revolution. Within a highly volatile environment that included repression of civil society organisations and democracy advocates, the project gave special emphasis to training in the use of social media to stimulate citizen journalism and free exchange of thoughts. Overall the project was relevant in view of the focus on youth which was well supported by baseline assessments that identified low youth participation in democratic processes. It was also important in view of the overall political environment leading up to elections during the time of the project implementation. The focus on social media was also relevant and effective given the role it had played as a catalyst of the Arab Spring.
Evaluation Date
April 2013
Theme
Country