Project: Civil Society Support Initiative on Political Marginalization in the Niger Delta in Nigeria
Evaluation Date: December 2012
Report: [report link]
Lesson Learned:

A radio programme, based on a Democracy Roundtable, was produced and broadcast in four states. While the topic was relevant to the project, no matter how well-produced, a “one-off” radio broadcast will have done little to support project objectives. Properly planned, with programming produced with local communities on a continuing basis, and with links to community development activities, development broadcasting can be a very effective tool. If radio programming is selected as a core project activity, it must be well-integrated with other activities and be employed throughout the project.

Theme: Community activism
Project: Civil Society Support Initiative on Political Marginalization in the Niger Delta in Nigeria
Evaluation Date: December 2012
Report: [report link]
Lesson Learned:

The government advocacy component of the project was a useful follow-up to the training provided. However, in many cases, the meetings seemed provide only an initial opening for voicing concerns and then government representatives providing information on current activities. This is not engagement. There were exceptions, where more was accomplished, but it is apparent that what was critical was that the meetings actually took place. They represented the initial step, the opening, to what was expected to be a long-term dialogue. For this expectation to be realized, far more support and advice will be required, over a period of years, rather than months.

Theme: Community activism
Project: Civil Society Support Initiative on Political Marginalization in the Niger Delta in Nigeria
Evaluation Date: December 2012
Report: [report link]
Lesson Learned:

The decision by the grantee to stretch activities across all nine states in the Niger Delta diminished the level of investment available for activities at each project site. While the geographic span of activity increased the visibility of the project, it reduced the prospect for impact and enhancing prospects for sustainability of results. A more focused project, limiting activities to, perhaps, three states would have provided a more effective basis for testing and refining the methodology, and building the foundation for more ambitious efforts in the future.

Theme: Community activism
Project: Civil Society Support Initiative on Political Marginalization in the Niger Delta in Nigeria
Evaluation Date: December 2012
Report: [report link]
Lesson Learned:

Some 237 CSO activists were trained in civic and political education, exceeding the target of 180. Similarly, 185 women and young people were trained through the engagement seminars, also exceeding the target of 135. In its own review, the grantee concluded that the sessions on participation and on media engagement were the most successful, in that they provided entirely new and practical knowledge, which trainees could apply readily. There was also a positive response from trainees to the module on democracy monitoring. In a number of cases, those supported by the project were motivated to take further action. Most often, this involved “stepping down” the training to other members of their networks.

Theme: Community activism
Project: Nigeria Procurement Monitoring Project
Evaluation Date: April 2012
Report: [report link]
Lesson Learned:

The project workshop covered a great deal of complex and challenging material on an intensive basis over two long days. Although materials were circulated in advance, according to participants, only those with a good prior knowledge of procurement and some understanding of the legal provisions of the Public Procurement Act would have been able to benefit fully from the workshop. Given the centrality of this activity to the project, it would have been sensible to eliminate at least one other activity in order to fully support this one.

Theme: Interaction with government
Project: Nigeria Procurement Monitoring Project
Evaluation Date: April 2012
Report: [report link]
Lesson Learned:

Ongoing activities require external funding. Given the need to maintain independence to ensure the credibility of its activities, accepting funding from the government is not an option for the grantee Although some of the longer-established NGOs are able to support some level of monitoring activity from their own resources, inevitably, the overall level of monitoring of procurement activity will decline without additional dedicated funding. Further, there is regular turnover in CSO ranks, and the level of knowledge required to be an effective monitor is significant.

Theme: Interaction with government