Project: Towards a better electoral process in Mongolia
Evaluation Date: November 2011
Report: [report link]
Lesson Learned:

The project accomplished its list of tasks, however its design was too ambitious for the resources available and some activities were only marginally accomplished. This included the training for police, judges and media, and the trainer-of-trainer (TOT) aspect of observation training. The loss of focus on TOT limited the project’s potential reach and effectiveness. These areas remain critical ones, especially for the justice sector.

Theme: Community activism
Project: Gender Equality and Equity - Follow Up to CEDAW and Romani women
Evaluation Date: November 2010
Report: [report link]
Lesson Learned:

There was a lack of continuity and follow-up in some areas of project work. This suggests that the project tried to include too many elements within a single project with limited resources. In the future, it is recommended that RCS be prepared to make some difficult choices in determining priorities, in order to ensure that adequate resources (including management time) are assigned to all project resources. The grantee would have benefited from advice about the benefits of focusing and concentrating its efforts on a shorter list of components, each pursued further, thus enhancing the prospect for impact.

Theme: Women's empowerment